P and Q together complete a piece of work in x days. If P alone completes the work in (x + 3) days and Q alone completes the piece of work in (x + 12) days, what is the value of 'x'?

Edit edit

A

8

B

6

C

12

D

4

উত্তরের বিবরণ

img

Unfavorite

0

Updated: 2 weeks ago

Related MCQ

Three workers can do a job in 6 days. Two of the workers work twice as fast as the third. How long would it take one of the faster workers to do the job himself?

Created: 2 weeks ago

A

15 days

B

18 days

C

24 days

D

12 days

Unfavorite

0

Updated: 2 weeks ago

Rafi and Shafi can paint a room in 4 days. Shafi can do it alone in 6 days. How many days will Rafi take to paint the room alone?

Created: 1 week ago

A

12 days

B

10 days

C

15 days

D

9 days

Unfavorite

0

Updated: 1 week ago

15 workers can build 45 chairs working 6 hours per day. How many extra workers are required to produce 60 chairs working 4 hours per day?

Created: 1 week ago

A

0 workers

B

10 workers

C

12 workers

D

15 workers

Unfavorite

0

Updated: 1 week ago

Links

Home

Exams

Live Exam

© LXMCQ, Inc. - All Rights Reserved

Developed by WiztecBD